Change the date tasks starts and finish in MS Project Web Access

E

eric

Hi!

When a user logs onto my MS Project Web Access 2003 server, they are not
able to change the dates for the tasks under the menu "View my tasks".
However viewing/adding Notes, changing the "% Work Complete" goes just fine
under the same menu.

Does anyone know why this does not work? Thanks :)
 
D

Dale Howard [MVP]

Eric --

It is working as expected. Microsoft's assumption is that only the project
manager should be able to change the Start or Finish date to a task, thus,
team members are not allowed to edit those fields.

If you wish for the team members to enter an Actual Start and Actual Finish
date for their assignment work, your Project Server administrator will first
need to add those extra columns to the Timesheet view in PWA. Refer to the
following link for the steps you will need to follow as well:

http://www.projectserverexperts.com/Shared Documents/changetimesheet.htm

Hope this helps.
 