Change the project manager

P

Paul Toman

I have published a project and my team are sending me task updates
regularly. Now I want to change the "project manager" so that the updates
go to someone else for approval. Any idea how I do this?
 
K

Kevin

Paul,

Have the new PM open the project in MS Project and click
on Collaborate, Publish, Republish assignments. This
will "assign" this project to them and also update them
with any new changes from the team. You should also
change the "owner" of the project in "Project Center"
within the Web Access Client. Hope this helps

Kevin
 
K

kevin

Sorry - Forgot the most critical part. While in
Collaborate, Publish, Republish assignments - you need to
check "Become the manager for these assignments."
 