M
Marina
I added some tasks to a resource who was at 100% max units.
I realized that the resource was not available 100% but only 50%.
After changing the max units in the resource view, the tasks still say 100%
for that resource.
I tried levelling, but I get a message stating that the overallocation
cannot be resolved. I do not want to change each task individually (there
are too many).
How do I fix this?
Marina
I realized that the resource was not available 100% but only 50%.
After changing the max units in the resource view, the tasks still say 100%
for that resource.
I tried levelling, but I get a message stating that the overallocation
cannot be resolved. I do not want to change each task individually (there
are too many).
How do I fix this?
Marina