G
Gwen
We changed the default project(Standard) calendar to a
different calendar called "flint".
For each resource we changed the standard calendar to the
new customized calendar "flint".
The project was republished after making the changes.
After accepting an update from a resource, all resource
calendars were changed back to the Standard calender and
all the changes that were on the flint calendar were
lost.
We had to go back and change all the resources back to
the "flint" calendar again.
Why did the resource calendars change?
If you change resources within a project, do the changes
get updated on the server? Or do we have to make all
resource calendar changes only in the resource global
template?
If the resource calendar is changed in one project,
shouldn't the other projects see these changes in their
resource calendars too? It appears not to working
correctly or as expected.
different calendar called "flint".
For each resource we changed the standard calendar to the
new customized calendar "flint".
The project was republished after making the changes.
After accepting an update from a resource, all resource
calendars were changed back to the Standard calender and
all the changes that were on the flint calendar were
lost.
We had to go back and change all the resources back to
the "flint" calendar again.
Why did the resource calendars change?
If you change resources within a project, do the changes
get updated on the server? Or do we have to make all
resource calendar changes only in the resource global
template?
If the resource calendar is changed in one project,
shouldn't the other projects see these changes in their
resource calendars too? It appears not to working
correctly or as expected.