Changing baseline date in MSP tables

P

Philippe Feugier

MSP 2002
I have store a baseline today, but I will it to be tagged with another date,
say the initial date of the project for example.
Is it possible to change it by editing one off the MSP_ tables ???
Thanks,
 
J

Jim Aksel

No. The best you can try is to set system time clock for that date and try
it again. That probably will not work either.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 