Changing report progress method

J

Jesper Bødtkjer

Hi,

When a project has once been saved with method "Percent of work complete" I
cant chace it to "Hours done per time period". I have tried changing the
method and republish the plan.

Any Ideas ?

Regards,
Jesper
 
D

Dale Howard

Jesper --

To change the method of tracking progress for the project, are you doing it
by clicking Tools - Customize - Published Fields? You must either do this,
or you must have your Project Server administrator change the method of
tracking progress for every project, and he/she should also lock down the
tracking settings.

When you try to republish the plan, do you click Collaborate - Publish -
Republish Assignments? This is the correct method for republishing a
project once you have changed the tracking method, as this method will
"push" the new tracking settings out to PWA on each user's timesheet.

Let me know and I'll try to help you.
 
J

Jesper Bødtkjer

Hi Dale,

Thanks a lot.

Actually I did exactly as you described, but I succeded now when I tried on
a new dummy project. The reason I did not realize this previously was, that
I looked at a completed task, where the change in reporting method does not
kick in -which does not seem unreasonable, since no additional entries are
expected on that task.

Regards,
Jesper
 