Changing Resource Usage Grid

R

Rick

Hello,

I'd like to display the remaining work in the resource usage grid rather
than work. I see the actual work may be displayed along with work, but would
rather not have to do the calculation to determine remaining work.

Is there a method to display remaining work in the grid?

Thanks.
 
D

Dave

Rick said:
Hello,

I'd like to display the remaining work in the resource usage grid rather
than work. I see the actual work may be displayed along with work, but would
rather not have to do the calculation to determine remaining work.

Is there a method to display remaining work in the grid?

Thanks.

You could export it to Excel and do the calculation there, but it is a
bit clunky.
 