changing settings to non-standard work week

A

alm80

Hello,
I need to change the working week to start on Sunday, and end on Thursday,
so that Friday and Saturday are days off. When I change this in "Change
Working Time", this has no effect on the calendar itself. I see
Saturdays/Sundays as days off. Is there any way to change also the visual
settings of the calendar to reflect this change. I can set those manually
with non-standard working time, etc. But it's a lot of work for multi-month
projects. I'd like this option to be set as default.
 
H

HansH

Using "Change Working Time", you can specify the work week you need
(Friday = non-working and Sunday = specific working times).
To visually show these changes in the Gantt Chart, right-click the Gantt
Chart and select Non-Working Time. You can specify the calendar to use
for showing non-working time.

The Task Usage and Resource Usage view however, use the 'Standard'
calendar for showing non-working time. So no option to show non-working
time from a different calendar in those views.

I hope this helps,
Hans

Projectopolis <http://msepm.hsquared.be>
 
J

JulieS

One quick clarification. The display of non-working time in the Task
and Resource Usage views can be changed through Format > Timescale,
Nonworking time tab.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
J

JulieS

Not to worry Hans. We all forget stuff :) Thanks so much for helping
the growing community of users.

Julie
Project MVP
 
A

alm80

Thanks for the help. The issue is fixed now :)

JulieS said:
Not to worry Hans. We all forget stuff :) Thanks so much for helping
the growing community of users.

Julie
Project MVP


.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top