L
Luc Overdulve
I've searched all over for this strange behavior but I cannot find
anything about it...
In my plan there are only Tasks with Type=Fixed Duration and Effort
Driven=No.
Some Tasks have one of more Resources (type=Work) connected with
Calendar=Project Calendar.
One of the earliest tasks, planned to be started back in January will
probably start now next week (from 22nd Feb), so while updating the
plan I have to change that Start Date and after that all FS connected
tasks will start at least as many days later as the duration of the
changed task. When doing this in Project 2003 this works fine.
In Project 2007 however there happens so much more! Many tasks now
have a changed Duration too and/or the amount of Work is changed. I
don't understand why this is happening (only) in Project 2007.
Because I did not succeed in finding more about this on the world wide
web of this group, I decided to post this question in here!
Thanks a lot for any suggestion(s)!
Luc (NL)
anything about it...
In my plan there are only Tasks with Type=Fixed Duration and Effort
Driven=No.
Some Tasks have one of more Resources (type=Work) connected with
Calendar=Project Calendar.
One of the earliest tasks, planned to be started back in January will
probably start now next week (from 22nd Feb), so while updating the
plan I have to change that Start Date and after that all FS connected
tasks will start at least as many days later as the duration of the
changed task. When doing this in Project 2003 this works fine.
In Project 2007 however there happens so much more! Many tasks now
have a changed Duration too and/or the amount of Work is changed. I
don't understand why this is happening (only) in Project 2007.
Because I did not succeed in finding more about this on the world wide
web of this group, I decided to post this question in here!
Thanks a lot for any suggestion(s)!
Luc (NL)