Changing view in update tab

J

Josh

Hello,

In Project 2003, I would like to change the view on the update tab to
re-organize the tasks to be approved by resource then project rather than by
project then resource.

Is this possible?

Thanks,
Josh
 
D

Dale Howard [MVP]

Josh --

The Project Server administrator cannot configure the View shown on the
Updates page. Instead, each PM will need to modify the display of the
Updates page by doing the following:

1. Navigate to the Updates page.
2. Click the Filter, Group, Search tab.
3. Set the Group By value to Project.
4. Set the Then By value to Resource.
5. Click the Filter, Group, Search tab again to collapse the section.

Hope this helps.
 