Changing View Resource Assignments

M

Miguel

Hi,
Is there any way of changing the TimeSheet format in the View Resource
Assignments?
I would like to remove Act. Work row and just let the Schedule Work row.
thanks
jrs
 
D

Dale Howard [MVP]

jrs --

It is not possible to remove the Actual Work line. Available options allow
you to add the the Schedule Work line and the Summary Tasks line, but not to
remove the Actual Work line. Sorry.
 
M

Miguel

Hi Dale,
I have a project that has had a change in the the allocation of a resource.
The person who was firstly assigned for a task in this project was transfered
to another project.
Therefore, I deleted his contribuition on the tasks he was going to
participate. Then I removed him from the 'Team Resource' panel. After this, I
clicked in the
Collaborate > Publish > All Information
and then in the
Collaborate > Publish > Repulish Assignments (with the 'Overwrite Actual
Work Entered by Resources' enabled).

After this I went to the PWA and in the 'View Resource Assignments' I
choosed the resource I've removed from the project. The problem is, that it
still appears the allocation of this resource on the project (wich he was
removed) with an amount of hours in the 'work' row.

Any idea of solving this issue?

Thanks Miguel
 
D

Dale Howard [MVP]

Miguel --

Is it possible he/she was assigned to tasks that are completed?
 
D

Dale Howard [MVP]

Miguel --

Well, for starters why don't you open the project, apply the Resource Usage
view, and see if the resource is still in the project assigned to completed
tasks?
 
Top