Checked-out project

I

Itzik

I had closed a project without saving it and from some
reason the project stayed as checked-out.
When I go to "Check in enterprise projects" I don't see
him.
What do I need to do in order to realese this project?
Thanks
 
H

Hugues Perron

Hi,

For what I know, you will have to use a sql query to change the column
PROJ_CHECKEDOUT in the MSP_PROJECTS table. For the problem project change
the value from 1 to 0. You can use Enterprise manager.

WARNING : Before doing any change directly to the database, make a backup
!!!!

Hugues
 
D

Dominic Moss

Itzik,

2 things - firstly I would have expected a prompt if you attempted to close
an altered file without saving it. Secondly have you changed any user
information about yourself within PWA - I have seen cases where either the
authentication method has been changed or other edits to user information
have been made in PWA and existing checked out projects are no longer
associated with the changed identity, they exist in a sort of limbo as they
cannot be opened and cannot be checked back into the Enterprise.

--
Dominic Moss

www.projectability.co.uk

Helping people achieve more with Microsoft Project

Tel +44 8707 303 400