Thanks for all the info.
I've been experimenting and have set all remaining work to zero for tasks
in-progress - by making sure all resource assignments were set to zero
remaining work. This will create the check mark of completed on all their
assignments (and remove from timesheets when on "Current Tasks" view.
Where I'm not sure is for tasks that never started. They were in the
planning stages but not used later. People were assigned and the tasks were
baselined. Do I remove the resources first? Do I delete the tasks after
resources are removed? Will this kill the orignal baseline for these early on
planned tasks?
I'm aware that removing resources from a tasks will give an X in their
timesheets. I'm trying to figure out the best way to clean this all up and
have their timesheets clean as well (not showing any X tasks). I've read you
should make all the resources "proposed" to hide it from timesheets, but I'm
assuming that's the last step when all tasks are cleaned up first?
Any advice much appreciated.
- Show quoted text -
Hi -
Here's my 2 cents:
For each task that was not started (not needed), put the word
CANCELLED in caps at the end of the task name ( - CANCELLED). Leave
the baselines for those tasks as is. Set the work, duration and cost
for those tasks to 0. The reason you might not want to delete them, is
for historical purposes - when analyzing why you budgeted what you
did, etc., and original dependencies, it explains things to still see
the tasks there.
You can remove the resources and re-publish. When tasks get an 'X' in
people's timesheet, they'll just highlight each of those rows and
click 'Hide' and that'll be that. Microsoft's game of hide-and-seek in
PWA 'My tasks' is very sad. Once a child hides, he/she is never to be
found again.
So here's the next question: What do people do with the project itself
so it doesn't clutter up the File / Open list? Maybe rename to start
with Z_, so it's at the end? Maybe move to another instance of Project
Server, created for archives?
-Girlgeek