N
Nuala
On opening one of the project plans from project server 2003, we get a
message saying calculations cannot be performed with the task ID
number due to a circular reference. The message also refers to
successors and predecessors, but there are none!
On the task usage page, reources have blank assignements, i.e. the
task names have been deleted, yet there is baseline cost associated
with them
Actuals have been accepted into the plan, therefore in order no to
lose these, we cannot restore a previous backup.
Unfortunately we do not have a transaction log back up.
Has anyone got any suggestions are to how to remedy this?
Thanks in advance
Nuala
message saying calculations cannot be performed with the task ID
number due to a circular reference. The message also refers to
successors and predecessors, but there are none!
On the task usage page, reources have blank assignements, i.e. the
task names have been deleted, yet there is baseline cost associated
with them
Actuals have been accepted into the plan, therefore in order no to
lose these, we cannot restore a previous backup.
Unfortunately we do not have a transaction log back up.
Has anyone got any suggestions are to how to remedy this?
Thanks in advance
Nuala