Michael Longdin
I have a project that was complete in Dec of last year and a particular
resource has no more tasks assigned after that date.
However, when I open another (current) project plan which contains the same
resource, the resource views are showing several days work for that resource
during Jan/Feb/Mar 2007 for the old plan and therefore the overall effort
figures for that resource in 2007 are incorrect.
I am assuming (but I don't know) that this is because at some point my
original plan did have effort in for that resource for 2007 which I have
subsequently cleared but it has been cached somehow and is still being picked
up in the new plan.
Anyone know if this is the case and, if so, how I cna clear the cache for
that project? I have tried republishing the old plan but this hasn't resolved
it. (If it's relevant, the resource data showing in the web access views is
correct. Note also that I have 2 or 3 other current plans which contain this
resource and the same problen occurs in them)
resource has no more tasks assigned after that date.
However, when I open another (current) project plan which contains the same
resource, the resource views are showing several days work for that resource
during Jan/Feb/Mar 2007 for the old plan and therefore the overall effort
figures for that resource in 2007 are incorrect.
I am assuming (but I don't know) that this is because at some point my
original plan did have effort in for that resource for 2007 which I have
subsequently cleared but it has been cached somehow and is still being picked
up in the new plan.
Anyone know if this is the case and, if so, how I cna clear the cache for
that project? I have tried republishing the old plan but this hasn't resolved
it. (If it's relevant, the resource data showing in the web access views is
correct. Note also that I have 2 or 3 other current plans which contain this
resource and the same problen occurs in them)