We are on Project 2007 and our PM would like to close out a schedule to
updates in PWA. We found the option in PWA to close tasks to updates but is
there a way to select all tasks instead of having to check each one
individually? Is there another way this can be done. The PM wants the
schedule to still be viewed through PWA but no updates to be allowed. I
found other help topics here that suggested adding a project status field and
training the user to not update closed tasks - is there not a way to prevent
users from updating? Thanks.
Linda
updates in PWA. We found the option in PWA to close tasks to updates but is
there a way to select all tasks instead of having to check each one
individually? Is there another way this can be done. The PM wants the
schedule to still be viewed through PWA but no updates to be allowed. I
found other help topics here that suggested adding a project status field and
training the user to not update closed tasks - is there not a way to prevent
users from updating? Thanks.