Hi,
I would like to close a project for any updates (in 2003). I did the
following hopping that it would resolve my problem, it resolved half of it
but not all of it:
I created a new category, I added my "Team members" group to it and I set
all the permissions to Deny for them. I added the project that I wanted to
close to the list of project in this category. The result was that members
couldn't create any more new tasks on that project neither assign themselves
to a task on that project. That was what I want to, but members can still see
the project on "My Tasks" view and can update actual work on it, that's the
part I need to solve.
I know that in 2007 there is an option - Close tasks to update - that
apparently would do what I need...
Can anyone give me an advice to solve my problem please?

Thanks in advance,
Elsa
 