Closed projects showing up on timesheets

J

JenGoSto

I'm in MSPS 2003. My resources have a closed project's tasks showing up on
Current Tasks view in PWA. I have checked to ensure that the remaining work
in the schedule has been 0'd out and that the resources are marked to booked.
I have also used every publishing option. I still see these projects on
their timesheets.

Additionally, I see that some of the tasks showing up have Remaining Work
even though the remaining work in the schedule is 0 (and yes re-published
just to make sure).

Any thoughts? I am stumped and I would expect that PWA match the schedule.

Thanks!
 
W

Wharton Computer Consulting

Make sure that your tasks are set to 100% complete. This should zero out the
remaining work. Check to see and if not, set them to 0. Also, check that
finish date is not showing out in the future. If so, adjust according.
 
J

JenGoSto

Thx for taking the time to respond! Unfortunately, this didn't resolve the
problem. Any other thoughts??
 
Top