Closed tasks reopening with 2003 server upgrade

L

lkirkp

Many tasks that were closed in 2002 Pro mysteriously reopend when we upgraded to 2003 server. OUr internal analyst believes that this is related to having a resource on the task with 0 actual and 0 remaining work. The only way we have found to close these tasks again is by removing the resource, so now there is no record they were ever on the task. Is there a better solution to get these things closed again? We would have a lot of work ahead of us if this is the only solution
Thanks!
 