Closing off Time periods in Project Server?

R

Richard.Natividad

Hi,

Just a question, is there any way in Project Server I can close off
time periods?

Disable the ability for users to enter time into Past periods? I want
to close off time entry now for January and Feburary to maintain
what's in there now. Is there a feature that I can activate that
closes this off?

Regards,

Richard Natividad
 
M

Marc Soester [MVP]

Hi Richard,

I assume that you are using Project Server 2003. Under Admin > Customize
Project Web Access you will be able to set Managed time periods. This will
allow you to close periods.
I hope this helps
 
R

Richard.Natividad

Hi Richard,

I assume that you are using Project Server 2003. Under Admin > Customize
Project Web Access you will be able to set Managed time periods. This will
allow you to close periods.
I hope this helps
--
Marc Soester [MVP]