G
Gina
Hello,
I have a question regarding closing tasks on Project Server. Currently our
plan is a fixed duration plan due to the type/nature of the project. When i
need to close a task with actual hours applied, the task will close.
Using Project server, I will then publish and Sync the plan to make sure i
have everything updated. I can close a task no problem when i have actual
work applied. However the issue I am running into is tasks not closing or
staying closed out when no actual work was ever assigned or remaining work
was zeroed out becuase no work was necessary to complete the task.
I close the task and then go to publish it and the task will re-open up. I
have changed the task type to fixed work as sometimes that helps. However it
doesn't matter what the task type is. The tasks keep re-opening.
I was told to go into PWA and do an "Adjust Actuals' to resources on those
tasks. However i get an error message that says my login has expired, even
though i just logged into PWA.
Has anyone ever seen this issue within Project Server? An if so, What did
you do to keep tasks closed. Currently is keeps showing we have tasks due
but are truly not due. Should of been closed 3-4 months ago. But keep
re-opening.
HELP.
Thank you in advance.
Gina
I have a question regarding closing tasks on Project Server. Currently our
plan is a fixed duration plan due to the type/nature of the project. When i
need to close a task with actual hours applied, the task will close.
Using Project server, I will then publish and Sync the plan to make sure i
have everything updated. I can close a task no problem when i have actual
work applied. However the issue I am running into is tasks not closing or
staying closed out when no actual work was ever assigned or remaining work
was zeroed out becuase no work was necessary to complete the task.
I close the task and then go to publish it and the task will re-open up. I
have changed the task type to fixed work as sometimes that helps. However it
doesn't matter what the task type is. The tasks keep re-opening.
I was told to go into PWA and do an "Adjust Actuals' to resources on those
tasks. However i get an error message that says my login has expired, even
though i just logged into PWA.
Has anyone ever seen this issue within Project Server? An if so, What did
you do to keep tasks closed. Currently is keeps showing we have tasks due
but are truly not due. Should of been closed 3-4 months ago. But keep
re-opening.
HELP.
Thank you in advance.
Gina