coasting

R

reby

I am a newcomer in this field, no body teach me how to do it. right now i am
trying to do a project coasting, but i got a problem eg: site settingout i
allowe one surveyour and two worker. but in task information table i go to
resources i can select one worker only, so that i can get one worker rate
only if i want more than one worker how i can do.

thanks,

reby
 
F

Francisco Alcala

Hi.

Change the assignment of the worker to 200% only on that task.

Hope it helps.