A
Arthur
Hi Group,
I don't think my original post worked, so here's
another...apologies if you got this twice.
I wrote the code below to graphically display the slippage
of my tasks depending on its status against the baseline.
Unfortunately I can't get it to run (as displayed by the
error message).
If you are able to shed some light on this for me; please
do.
Regards, Arthur.
Switch([Enterprise Project Number28]=-1,"Rvsd Comp Date
Not Set",[Enterprise Project Number28]=0,"Project at
Stage0",[Enterprise Project Number28]=1,"On Schedule",
[Enterprise Project Number28]=2,"Slippage <=30 days",
[Enterprise Project Number28]=3,"Slippage >30
days",True,"Formula has error")
I don't think my original post worked, so here's
another...apologies if you got this twice.
I wrote the code below to graphically display the slippage
of my tasks depending on its status against the baseline.
Unfortunately I can't get it to run (as displayed by the
error message).
If you are able to shed some light on this for me; please
do.
Regards, Arthur.
Switch([Enterprise Project Number28]=-1,"Rvsd Comp Date
Not Set",[Enterprise Project Number28]=0,"Project at
Stage0",[Enterprise Project Number28]=1,"On Schedule",
[Enterprise Project Number28]=2,"Slippage <=30 days",
[Enterprise Project Number28]=3,"Slippage >30
days",True,"Formula has error")