Code Question

A

Arthur

Hi Group,

I'm having a problem with the code below. It was created
to show schedule slippage but does not run correctly (as
displayed with the error at the end). If you can help,
please do.

Regards, Arthur.

Switch([Enterprise Project Number28]=-1,"Rvsd Comp Date
Not Set",[Enterprise Project Number28]=0,"Project at
Stage0",[Enterprise Project Number28]=1,"On Schedule",
[Enterprise Project Number28]=2,"Slippage <=30 days",
[Enterprise Project Number28]=3,"Slippage >30
days",True,"Formula has error")
 
Top