Tim Ivey
I have to use Project Web Access to collect actual hours per tasks.
So here is the senario.
I have a task that is 3 weeks long and I plan on working 4 hours per week
Problem.
If I work 6 hours in the first week and enter this information through PWA, The plan is updated with 4 actual hours in week 1 and 2 actual hours in week too instead of placing all of the hours in week 1.
Do I have a setting wrong. Is this the design of this program.
Any Help, Advice or Guidance is greatly appreciated