John,
I would like all of the task bar to change colour, I know it sounds like I'm
looking for the critical path (which turns red), but unlike a critical path
I will have as many as 6 or 7 tasks that will fit into the criteria of being
over the limited duration allowed. I was hoping that the Flag customizing
would do it, but it only looks at the druation of each task, were as I want
it to look at the collective duration of all linked tasks. And in a simple
manner, VBA is something I don't know about and probably wont have the
opportunity to learn. The project(s) I work with are for equipment turn
arounds or shutdowns of only 8 to 12 hours duration, sounds like micro
managing? it is. The culture is that way here. So if there is a formula that
I can use in a customized field, it would be great.
TIA, Colin D.
: In article <
[email protected]>,
:
: > Hi, I can get an individual bar to change colour when the Duration is
more
: > than 6 hours (using A customized Flag), but how do I get it to change
when,
: > say Joe Blow does several tasks (4 - 2 hour tasks) which create a
collective
: > duration of more than 6 hours?
: > TIA, Colin D.
:
: Colin,
: So which of the 4 tasks do you want to change color? And are you sure
: you want to detect Duration? It sounds more like you might want to
: detect Work for a given resource; say a different bar color for those
: tasks that have Joe working 6 or more hours in a single work day.
:
: Sometimes a formula in a customized field will help get what you need,
: but if formula starts to get complex or involves doing something to more
: than just the task where the formula resides, then VBA will most likely
: be required.
:
: Hope this helps.
: John
: Project MVP