O
Onno
Hi, I am fairly new to MS Project (2007). I am trying to setup a
planning for my team and I can’t find answers to the following
questions:
1) The team workweek is 40 hours, so the default calendar is ok.
However, I myself work 36 in 4x9h. What is best: a) change my personal
calendar to 4x9 (1 day free/week), or b) set the Max. Units on the
Resource Sheet for myself to 90%? What are the pros and con’s of both?
2) I use effort-driven scheduling. When I assign 2 resources to a
task, the duration halves. This is what I expect. However, if I assign
a single resource for 50% to the task, the duration stays the same. I
would have expected that it would double?
3) If I remember correctly, previous Project versions had an ‘effort’
and a ‘duration’ column for tasks. I filled in my best estimation for
a task in effort, and Project calculated the duration based on the
assigned resources, holidays in the calendar, etc. I am a bit confused
as to what the ‘duration’ column in the gant chart now means. Where
did the distinction between effort and duration go?
4) What is the effect of marking an entered duration as an estimation?
(Either by entering it like ‘5days?’ or by checking ‘Estimated’ in the
Task Information dialog?
5) I thought that if I had a bunch of tasks and work-type resources, I
could just fill in the estimated efforts, link the tasks that have
dependencies and assign the resources. Project would then schedule,
dividing the time the resources have over the tasks. However, this
does not happen. Project just allocates the tasks resulting in
overallocated resources. Do I really have to check the Resource Graph
for each resource and each time frame myself to adjust the ‘Units’ on
assignments myself to prevent over allocation?
6) Nobody works 100% efficient. We have several weekly meetings,
interruptions for giving support, coffee breaks
etc. What is the
best strategy here? a) Try to calculate then into the estimations? b)
Reduce the Max. Units of each resource to say 80%, or c) Create a new
(“meetings, reviews, support, etc”) task for it. My previous project
leader used to do it like this in another planning tool, and I would
like to do it also like this. But if this means that I manually have
to lower the Units for each task to balance between this and the other
tasks, I don’t feel it’s the right way.
Many thanks for your answers. Please forgive me if these are noob
questions, I cannot find the answers in the help or otherwise online.
Regards,
Onno
planning for my team and I can’t find answers to the following
questions:
1) The team workweek is 40 hours, so the default calendar is ok.
However, I myself work 36 in 4x9h. What is best: a) change my personal
calendar to 4x9 (1 day free/week), or b) set the Max. Units on the
Resource Sheet for myself to 90%? What are the pros and con’s of both?
2) I use effort-driven scheduling. When I assign 2 resources to a
task, the duration halves. This is what I expect. However, if I assign
a single resource for 50% to the task, the duration stays the same. I
would have expected that it would double?
3) If I remember correctly, previous Project versions had an ‘effort’
and a ‘duration’ column for tasks. I filled in my best estimation for
a task in effort, and Project calculated the duration based on the
assigned resources, holidays in the calendar, etc. I am a bit confused
as to what the ‘duration’ column in the gant chart now means. Where
did the distinction between effort and duration go?
4) What is the effect of marking an entered duration as an estimation?
(Either by entering it like ‘5days?’ or by checking ‘Estimated’ in the
Task Information dialog?
5) I thought that if I had a bunch of tasks and work-type resources, I
could just fill in the estimated efforts, link the tasks that have
dependencies and assign the resources. Project would then schedule,
dividing the time the resources have over the tasks. However, this
does not happen. Project just allocates the tasks resulting in
overallocated resources. Do I really have to check the Resource Graph
for each resource and each time frame myself to adjust the ‘Units’ on
assignments myself to prevent over allocation?
6) Nobody works 100% efficient. We have several weekly meetings,
interruptions for giving support, coffee breaks
best strategy here? a) Try to calculate then into the estimations? b)
Reduce the Max. Units of each resource to say 80%, or c) Create a new
(“meetings, reviews, support, etc”) task for it. My previous project
leader used to do it like this in another planning tool, and I would
like to do it also like this. But if this means that I manually have
to lower the Units for each task to balance between this and the other
tasks, I don’t feel it’s the right way.
Many thanks for your answers. Please forgive me if these are noob
questions, I cannot find the answers in the help or otherwise online.
Regards,
Onno