S
Stretch
I am working on a proposal. This means an individual can be responsible for
several paragraphs in the statement of work (SOW).
I pasted SOW paragraph numbers separated by commas into a text field. No
problem.
Here is the text I want to paste:
3.2.7, 3.2.7.1, 3.2.7.1.1, 3.2.7.1.2, 3.2.7.2, 3.2.7.2.1, 3.7.2.2.2
However, when I made the text field a Custom Field, Project 2007 stripped
off everything after the first comma.
Is there any way to make this work in a custom field?
Thanks in advance.
several paragraphs in the statement of work (SOW).
I pasted SOW paragraph numbers separated by commas into a text field. No
problem.
Here is the text I want to paste:
3.2.7, 3.2.7.1, 3.2.7.1.1, 3.2.7.1.2, 3.2.7.2, 3.2.7.2.1, 3.7.2.2.2
However, when I made the text field a Custom Field, Project 2007 stripped
off everything after the first comma.
Is there any way to make this work in a custom field?
Thanks in advance.