E
Elena
Hi
What is the difference between % complete and % physical complete (in the
additional properties of task).
And how can I see formula which are used to calculate the percent of task
completness?
We have the following situation:
we have task with fixed duration and two peoples for this task. Duration 1
week (40 hours for each person), assumed beginning is Monday (8.01). But
first person began work at Friday (5.01), worked 10 hours. Second have worked
10 hours at Thursday (4.01). When we look at task completness for each person
we see - 25%/
But when we go tj the Project centre ant see the total completness we see -
27%.
What is the reason.
I try to understand this calculations, but I can't recieve the same figure
(27%) on paper.
Thank in advance
What is the difference between % complete and % physical complete (in the
additional properties of task).
And how can I see formula which are used to calculate the percent of task
completness?
We have the following situation:
we have task with fixed duration and two peoples for this task. Duration 1
week (40 hours for each person), assumed beginning is Monday (8.01). But
first person began work at Friday (5.01), worked 10 hours. Second have worked
10 hours at Thursday (4.01). When we look at task completness for each person
we see - 25%/
But when we go tj the Project centre ant see the total completness we see -
27%.
What is the reason.
I try to understand this calculations, but I can't recieve the same figure
(27%) on paper.
Thank in advance