% Complete Calculation with Managed Time Periods

K

Kevinb

We're using project 2003 and project server and having a problem with the %
complete column in project server.

We have set the default global template to automatically calculate the %
complete within our our projects.

Here's the issue: Within our project plans we have many tasks which are
just tracking tasks. (They have zero work associated with them) Project
server is not allowing us to update these tasks to 100% complete. (When we
publish - the tasks revert back to zero percent complete)

Is there a way to force the system to accept these tasks as 100% complete
when using managed time periods and automatic calculation?
 
D

Dale Howard [MVP]

Kevin --

Your problem with manually setting milestones to 100% complete is a bug that
was fixed in SP1. You should immediately upgrade to SP2 for all of the
latest bug fixes to the system on both Microsoft Project Professional and
Project Server. Hope this helps.
 
Top