% Complete changes to less than 100%

J

Jim G

I'm using Project 2002 Professional. There are several tasks in our plan
that are 100% complete. When I save the plan to my harddrive the % Complete
changes to less than 100% complete on these tasks.
 
J

Jim

Look at these areas:

1. Look at the Remaining Work field and make sure that it is 0.

2. Check to make sure that the task does not have a predecessor. I have
noticed that on my projects, if the task has a predecessor that has not yet
completed, then it will not close the task, leaving it in complete even
though the Remaining Work shows 0.
 
J

Jim G

The point is that the task is 100% complete (which means 0 remaining work)
while in Project Server. I save the file to my hard drive and the % complete
changes to less than 100% Complete (in the 90's usually) and remaining work
is still 0.
 