I either don't understand something or I have something
mis-configured in my PJ2003 server.
If I update the % Complete for a task in a project using
Project 2003 Pro and save it to the project server, then I
go look at that same task in Project Web Access, it
doesn't show the % Complete update I did in Proj Pro.
Likewise, if I update a % Complete in Project Web Access,
Approve it, then go look at that same task in Project 2003
Pro, it doesn't show the update there.
It's almost like the % Complete in Project Server and the
% Complete in the individual Project are different fields
that have nothing to do with one another.
I've tried both the % Complete and the % Work Complete
with the same results.
What am I doing wrong?
mis-configured in my PJ2003 server.
If I update the % Complete for a task in a project using
Project 2003 Pro and save it to the project server, then I
go look at that same task in Project Web Access, it
doesn't show the % Complete update I did in Proj Pro.
Likewise, if I update a % Complete in Project Web Access,
Approve it, then go look at that same task in Project 2003
Pro, it doesn't show the update there.
It's almost like the % Complete in Project Server and the
% Complete in the individual Project are different fields
that have nothing to do with one another.
I've tried both the % Complete and the % Work Complete
with the same results.
What am I doing wrong?