They do exist on Task level.
They do not exist on assignment level.
The why is because Microsoft did not put this in the software, so it doesn't
come out.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620