% Complete in Task Usage View

G

Gary Johnson

Can anyone tell me why the %Complete and Cumulative %Complete fields do not
work in Task Usage ?

Thanks

Gary
 
J

Jan De Messemaeker

Hi,

They do exist on Task level.
They do not exist on assignment level.
The why is because Microsoft did not put this in the software, so it doesn't
come out.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
G

Gary Johnson

OK Got it Thanks !

Gary

Jan De Messemaeker said:
Hi,

They do exist on Task level.
They do not exist on assignment level.
The why is because Microsoft did not put this in the software, so it doesn't
come out.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top