EmilyB
I was hoping that someone could help me with an odd
problem.
We are running Project Pro 2002 and Project Srv 2002.
Internally we have created some fairly simple templates to
be used for new projects.
In addition, we have decided to only use the Actual Work &
Remaining Work options for our time tracking.
We have noticed that if a project manager creates a new
project based on one of our templates and then publishes
the assignments, when the resource submits their work, the
%complete value is not calculated and if they happen to
record all the work creating a completed task then the
Actual Finish date is not generated. Actual Cost and
Actual Work are properly calculated, but %complete is
not. When a user looks at the details of a task then the
remaining work is 0.
If this entire scenerio is recreated using a brand new
blank project, not based on a template, then everything is
calculated as it should be?
Has anyone seen this or does anyone have any ideas?
Thanks,
Emily
problem.
We are running Project Pro 2002 and Project Srv 2002.
Internally we have created some fairly simple templates to
be used for new projects.
In addition, we have decided to only use the Actual Work &
Remaining Work options for our time tracking.
We have noticed that if a project manager creates a new
project based on one of our templates and then publishes
the assignments, when the resource submits their work, the
%complete value is not calculated and if they happen to
record all the work creating a completed task then the
Actual Finish date is not generated. Actual Cost and
Actual Work are properly calculated, but %complete is
not. When a user looks at the details of a task then the
remaining work is 0.
If this entire scenerio is recreated using a brand new
blank project, not based on a template, then everything is
calculated as it should be?
Has anyone seen this or does anyone have any ideas?
Thanks,
Emily