% Complete not Calculating

P

ProjectController

For some reason, my project has stopped calculating % Complete. I've checked
Tools\Options\Calculation\Automatic. Also, the Actual Duration and Remaining
Duration are not being updated either. Actual Duration is always zero even
though it’s well into the task. So Remaining Duration equals Duration.
 
J

JNB

Hi ProjectController:

Check the option "Updating task status updates resource status", it should be
checked by default:

Tools | Options... > Options dialog box | Calculation tab | [x] Updating
task status updates resource status

Hope this helps.

Best Regards.
-JNB
 