% complete not updated in timesheet

N

nfo

Hi,

I have a problem in PWA. The timesheet doesn't show % completed and all
actual information that has been updated in Project Pro by a Project
manager.
I'm using project server sp2a, Project 2003 Sp2, and Percent of work
complete method.
I can however find these changes when I display the project in Project
Centre.
It seems that there are no synchronization betwen timesheet and project
center.
I tried to republish and publish a project plan with no success, The
timesheet remain the same.
Thanks for your help
 
N

nfo

Hi Dale,

Thanks for your quick response.
I reffer to the Faq, but in my case it doesn't apply.
The calculation tab is correct
In fact when I update a task in PWA using % completed method, everything is
all right. The % completed is shown on both timesheet and Project 2003 Pro
But when a project manager want to update his tasks from Project 2003 Pro,
and then save his project, these updates doesn't appear on his timesheet
which remains identical to what she was before update.
May be I forgot something
 
D

Dale Howard [MVP]

nfo --

I misunderstood your original question. If the PM is entering his/her own
actuals manually in the Microsoft Project plan, he/she needs to republish
the assignments using:

1. Click Collaborate - Publish - Republish Assignments
2. Select the "Overwrite actual work entered by resources" option
3. Click OK

The above steps will "push" the actuals from the Microsoft Project plan to
the PM's PWA timesheet. Hope this helps.
 
N

nfo

Thank you Dale a thousand times. I forgot "Overwrite actual work entered by
resources"
It works fine now
 