N
nfo
Hi,
I have a problem in PWA. The timesheet doesn't show % completed and all
actual information that has been updated in Project Pro by a Project
manager.
I'm using project server sp2a, Project 2003 Sp2, and Percent of work
complete method.
I can however find these changes when I display the project in Project
Centre.
It seems that there are no synchronization betwen timesheet and project
center.
I tried to republish and publish a project plan with no success, The
timesheet remain the same.
Thanks for your help
I have a problem in PWA. The timesheet doesn't show % completed and all
actual information that has been updated in Project Pro by a Project
manager.
I'm using project server sp2a, Project 2003 Sp2, and Percent of work
complete method.
I can however find these changes when I display the project in Project
Centre.
It seems that there are no synchronization betwen timesheet and project
center.
I tried to republish and publish a project plan with no success, The
timesheet remain the same.
Thanks for your help