Complete or update tasks assigned to other users

R

Richiee

Can a user (e.g. a Project Manager) complete or update the tasks assigned to
other user?
 
B

bill

The project manager can open up project professioanal and go into the
resource usage view and make the time entry there
 
R

Richiee

That is Ok, but when I log on in PWA as a user originally assigned the tasks
appear 0% complete in the My Tasks View.
 
J

Jo

Richiee -
How did the PMs make the updates in Pro? Did they use the Resource Usage
view? Did they Republish Assignments, with the checkbox to overwrite actual
work?
--Jo
 