Complete Through

A

Atilla Otaner

Hi,

Does anyone know how the "complete through" is calculated
for the "Summary" or "Project Summary" level tasks?

For a project, some tasks has complete through set to
current day other tasks is a not. The Complete Through
seems to take an average?

Thanks,
/// Atilla
 
G

Gérard Ducouret

Hello Atilla,

At the Summary level, the "Complete through" is calculated as the ratio
between the sum of all subtasks Actual durations/ the sum of all subtasks
Durations.
When there are overlaps between subtasks, this calculation seems confusing.

Gérard Ducouret
 
A

Atilla Otaner

Thanks Gerard!
That explains a lot.
/// Atilla
-----Original Message-----
Hello Atilla,

At the Summary level, the "Complete through" is calculated as the ratio
between the sum of all subtasks Actual durations/ the sum of all subtasks
Durations.
When there are overlaps between subtasks, this calculation seems confusing.

Gérard Ducouret