S1lverface
Can anyone help on this problem I have, which I am probably making sound more
difficult than it reall is : - I can see on the tasks summary bar that I have
a task duration of 100 weeks. I can see on the summary bar that I am 38%
Complete. If I am 50 weeks into the task I want to see a column and / or bar
showing me that I SHOULD BE 50% complete, compared with the actual 38%, so as
it is easy to see how far ahead / behind plan I am. this must take into
account the correct calendar for each task. !!!!
Cheers ;-(