Hi,
We use Project Server 2003, Project Web Access to enter time, and MS-Project
Professional 2003.
A task was completed on April 4. So, on April 5, I entered the date of
completion in the column "Actual Finish" in Project Server and re-published
new and changed assignments.
Meanwhile, people entered time on PWA. The only person assigned to the task
in question entered time on April 4 against that task.
On Monday April 9, I imported all the PWA time entered for the previous
week, saaved the project as prompted and then noticed that the task in
question has lost its completion date of April 4 and was now showing up as
"NA".
Can someone tell me why this happened?
Point to note: I know I am supposed to mark tasks complete by zeroing out
Remaining work instead of entering the date in Actual Finish, but then I do
not get the correct finish date. This is why I enter the correct date in
Actual Finish.
Thank you and cheers
We use Project Server 2003, Project Web Access to enter time, and MS-Project
Professional 2003.
A task was completed on April 4. So, on April 5, I entered the date of
completion in the column "Actual Finish" in Project Server and re-published
new and changed assignments.
Meanwhile, people entered time on PWA. The only person assigned to the task
in question entered time on April 4 against that task.
On Monday April 9, I imported all the PWA time entered for the previous
week, saaved the project as prompted and then noticed that the task in
question has lost its completion date of April 4 and was now showing up as
"NA".
Can someone tell me why this happened?
Point to note: I know I am supposed to mark tasks complete by zeroing out
Remaining work instead of entering the date in Actual Finish, but then I do
not get the correct finish date. This is why I enter the correct date in
Actual Finish.