Completing a Task manually

S

Snig

Hi

This is the scenario: suppose a task has been alloted 10 hours.
However, in Project Server Resources can put more hours than that. But
whenever the actual hours becomes equal to greater than whatever is
alloted (10 hrs in this case), the task automatically gets completed.

How to block this behavior? I want my project managers to manually flag
the tasks as completed when they are notified.

Thanks in advance.
 
M

Mike Glen

Hi Snig ,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web address:
http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP




wrote:
 
Top