Hi!
Is there a way to automatically format text if the value of Finish Variance
(difference between Baseline Finish and Finish date-values) is more than 0
days?
Thank you.
 
J

John

Melissa said:
Hi!
Is there a way to automatically format text if the value of Finish Variance
(difference between Baseline Finish and Finish date-values) is more than 0
days?
Thank you.

Melissa,
Well yes, there is a way. As a matter of fact there are a couple of ways
but neither is necessarily convenient nor simple. Project does not have
very much flexibility with regard to text formatting so to automate text
formatting either a formula with paste linking or a VBA macro will be
required.

How about an alternate approach that is a lot easier. Instead of
directly formatting the text, try using a custom field with indicators.
It won't format the text but it will give you a unique color indication
of the Finish Variance you want. For more information on setting up
custom fields check the Project Help file or go to our MVP website at:
http://project.mvps.org/mike's_tutorials.htm
and check out fellow MVP, Mike Glen's series on Project lessons and
techniques. Mike covers customizing in lessons 14 & 15.

Hope this helps.
John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads

Special RAG light 4
Division by "0" 4
MS Project. Real progress of the project, % complete 1
Baseline Finish empty 1
Adjusted Variance and VBA 6
OT RAG formula 2
schedule variance 5
Automatic Formatting 9

Top