Configure timereport

J

Janne

Hi,

How do wee configure the web to let the user only report
there time totaly/week, instead of report / day?

Using Project + Server 2003.

Thanks,
Janne
 
D

Dale Howard [MVP]

Janne --

Do the following:

1. Log into Project Web Access with Administrator permissions
2. Click the Admin menu
3. Click the Customize Project Web Access link
4. Select the "Hours of work done per day or per week" option at the top of
the page
5. Select the "Force project managers..." option in the Lock down defaults
section
6. Select the "Resources should report their total hours worked for a week"
option in the Time Period Settings section
7. Click the Save Changes button

Once you have done this, you will need to ask each of your project managers
to complete the following steps for EVERY one of their projects:

1. Open the project
2. Click Collaborate - Publish - Republish Assignments
3. Click OK

Doing so will "push" the new method of tracking out to each user's timesheet
in PWA. Hope this helps.l

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top