Janne --
Do the following:
1. Log into Project Web Access with Administrator permissions
2. Click the Admin menu
3. Click the Customize Project Web Access link
4. Select the "Hours of work done per day or per week" option at the top of
the page
5. Select the "Force project managers..." option in the Lock down defaults
section
6. Select the "Resources should report their total hours worked for a week"
option in the Time Period Settings section
7. Click the Save Changes button
Once you have done this, you will need to ask each of your project managers
to complete the following steps for EVERY one of their projects:
1. Open the project
2. Click Collaborate - Publish - Republish Assignments
3. Click OK
Doing so will "push" the new method of tracking out to each user's timesheet
in PWA. Hope this helps.l
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"