When you assign a resource to a task, Project assumes they will work at the
same level until done, ir, if you assign someone to a task with 5 days
duration at 50%, they will work on it at 4 hours per day for all 5 days.
But the real world is not so orderly. The task might require 6 hours the
first day, 3 hours the second, 4 hours the third and so forth. The pattern
of work, the way the rate of progress changes with time, is the work
contour.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
parul said:
What is the significance of COntours?