We use MS Project Professional 2003 and PWA for recording actuals in Project
Server.
A manager copied an existing plan that contained actuals, and published the
copied plan onto server. When prompted to synch actuals, he did.
Unfortunately, he now has Actual Work Protected locked into the new plan,
even though no actuals have ever been recorded/approved for this particular
plan.
How do I fix this?
Many thanks
Nicola