Copy non-working information of all resources from calendar to a project

B

BertVI

We want to create a project that contains all the non-working
information of our resources, copied from the calendar.
The purpose of this project is to display a global overview of our
resources unavailability (holidays, vacation).
Is it possible to do this with MS Project 2003 automatically?

I'm quite new to this, so if I need to supply more information about
the problem, I will gladly comply.

Greetings,

Bert
 
D

Dale Howard [MVP]

BertVI --

There is no default way to do this in Project Server 2003. You would need
to write a macro in Project VBA for this purpose. Hope this helps.
 
B

BertVI

BertVI --

There is no default way to do this in Project Server 2003. You would need
to write a macro in Project VBA for this purpose. Hope this helps.

Thank you for the suggestion.
 