Copying a Baseline to another Baseline

B

Bob

We've decided to save our original baseline as Baseline10. Several weeks ago,
one of our PM's accidentally saved it as Baseline(0). How can I copy it to
Baseline10 now?

Thanks,
Bob
 
B

Bob

To answer my own question ....
I set up a Variance view showing Baseline Start and Baseline Finish. In this
view, I inserted columns for Baseline10 Start and Baseline10 Finish. Then
copy the field values from Baseline to Baseline10.

Don't know why I didn't think of this earlier. Vapor lock I suppose.

Bob
 