Hi,
i am looking for a correct way to enter actuals for a proj with all fixed
work type tasks. e.g. i have a task A which i baselined with following value
1. fist entered task name and work (effort estimated) as A and 16 hrs.
2. then entered the resource name and % availability as 25% to calculate the
duration as 8 days. Then baselined the values.
Can some one suggest what should i enter and in what order while updating
the actuals upon 100% completion of task. Following value i want to update -
name - Task A, Work - 20 hrs, duration - 10 days. I want the proj to adjust
the resource %ge.
I am basically confused with the order i should enter the value. With a
couple of hit & try, i manage to achieve the result but i want some one to
giude me the rules so that i can remember i do it in one go.
i am looking for a correct way to enter actuals for a proj with all fixed
work type tasks. e.g. i have a task A which i baselined with following value
1. fist entered task name and work (effort estimated) as A and 16 hrs.
2. then entered the resource name and % availability as 25% to calculate the
duration as 8 days. Then baselined the values.
Can some one suggest what should i enter and in what order while updating
the actuals upon 100% completion of task. Following value i want to update -
name - Task A, Work - 20 hrs, duration - 10 days. I want the proj to adjust
the resource %ge.
I am basically confused with the order i should enter the value. With a
couple of hit & try, i manage to achieve the result but i want some one to
giude me the rules so that i can remember i do it in one go.