Fixed duration task and associated time budgets....help

Discussion in 'Project' started by three_jeeps, Mar 18, 2015.

  1. three_jeeps

    three_jeeps

    Joined:
    Mar 18, 2015
    Messages:
    1
    Likes Received:
    0
    I am fighting with MS Project 2013 and cant figure out how to do this task:

    I am creating a schedule for a project. It is to be used as an estimate for planning purposes.

    What I want to do is list a number of Fixed Duration tasks and assign the task a budget in hours (For example the task may span 2 weeks duration but the amount of budgeted work days may only be 4 days the work can be done anytime during the 2 week period).

    I am guessing I can choose one of the 'built in' columns to capture the work budget for the task, but which one????

    Then I want to assign some people with a percentage of their time/week to each task. (I know how to do this...)

    Finally I want to add a column that will display, for each task, if the people I have assigned (with their respective % work) will be less than, equal to, or greater than the budgeted hours for that task. I don't know how to do this...any pointers???

    Any help is really appreciated.

    thanks
     
    three_jeeps, Mar 18, 2015
    #1
    1. Advertisements

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments (here). After that, you can post your question and our members will help you out.