Cost Baseline

A

Anya Blue

I can't see my cost baseline in the project summary. I have entered all my
task and resources along with rates.

??
 
J

JulieS

Hello Anya,

Have you actually save a baseline? Tools > Tracking > Save
Baseline. Did you add the Baseline Cost field to the table?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
A

Anya Blue

Hi Julie,

Where is the Baseline Cost field on the table? I think I may be missing that.
 
J

JulieS

Hello Anya,

The Baseline Cost field appears in the Cost table. You can also
insert the Baseline Cost field into any table through Insert >
Column.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 